Report ID: 19-015   
Type: Consent
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 1/9/2019 Final action: 1/9/2019
Recommended Action: Consider authorizing the General Manager to execute a funding agreement with the Metropolitan Transportation Commission (MTC) for the West Grand Avenue Transit Signal Priority (TSP) Implementation and Evaluation Project.
Attachments: 1. Att.1. W. Grand Ave Transit Improv. Supp., 2. STAFF REPORT
TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager
SUBJECT: West Grand Avenue Transit Signal Priority (TSP) Implementation and Evaluation Project

ACTION ITEM

RECOMMENDED ACTION(S):

Title
Consider authorizing the General Manager to execute a funding agreement with the Metropolitan Transportation Commission (MTC) for the West Grand Avenue Transit Signal Priority (TSP) Implementation and Evaluation Project.
Body
BUDGETARY/FISCAL IMPACT:

The MTC will provide $950,000 to close the TSP gap on West Grand Avenue between Maritime Street and 27th Street in Oakland and to relocate some bus stops.
In coordination with Caltrans, the City of Oakland, and AC Transit, MTC completed preliminary design of the project. The project will be programmed in the FY 2019-20 capital budget. Staff does not anticipate any District contribution other than staff time.

BACKGROUND/RATIONALE:

The West Grand Transit Signal Priority (TSP) Implementation and Evaluation project is part of the "Bay Bridge Forward" initiative. The project would improve bus operations on West Grand Avenue. There exists disconnected and untested TSP equipment in the corridor. The project will provide testing and integration of the TSP system on West Grand Avenue and relocate several bus stops to the far side of intersections.
MTC approached AC Transit about implementing the West Grand Avenue Project as part of the Rapid Corridors Project. Staff expects this will allow a seamless implementation of the West Grand/Grand Avenue TSP system and provide benefits from economies of scale in construction contracting and TSP equipment purchases.

ADVANTAGES/DISADVANTAGES:

Stakeholder coordination and preliminary design are complete. The project's implementation is fully funded and benefits from an economy of scale will be achieved by combining the project with the Rapid Corridors Project. Notwithstanding staff time, there are no disadvantages in approving the funding agreement.
The...

Click here for full text