Report ID: 20-111   
Type: Consent
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 3/11/2020 Final action: 3/11/2020
Recommended Action: Consider receiving the monthly construction progress and operational readiness report on the East Bay Bus Rapid Transit (BRT) project.
Attachments: 1. STAFF REPORT, 2. Att 1 BRT Costruction and Operational Readiness Report 3.11.pdf, 3. Master Minute Order

TO:                                          AC Transit Board of Directors                                          

FROM:                                          Michael A. Hursh, General Manager

SUBJECT:                     East Bay Bus Rapid Transit Project Progress Report                      

 

BRIEFING ITEM


RECOMMENDED ACTION(S):

 

Title

Consider receiving the monthly construction progress and operational readiness report on the East Bay Bus Rapid Transit (BRT) project.

Body

 

STRATEGIC IMPORTANCE:

 

Goal - Convenient and Reliable Service


The fully Implemented BRT project will provide sheltered, lighted and convenient waiting areas; raised platforms for level boarding; dedicated lanes, coordinated signals, and priority for reliable service.

 

BUDGETARY/FISCAL IMPACT:

 

Refer to Attachment 1 for the budget status on the construction contract and professional service contracts supporting the BRT Construction and to view the Funding-Expenditure Cost-to-Complete chart.

 

BACKGROUND/RATIONALE:

 

Refer to Attachment 1 for updates on Construction Progress, Operational Readiness, Public Outreach. Note that slide 5 in the attachment has transitioned from identifying the stations in interim condition to substantial completion progress.

 

ADVANTAGES/DISADVANTAGES:

 

This report is a monthly construction and operational readiness update and there are no associated advantages or disadvantages.

 

ALTERNATIVES ANALYSIS:

 

There is no analysis of alternatives required for this report.

 

PRIOR RELEVANT BOARD ACTION/POLICIES:

 

There are no relevant Board actions related to this report.                     

ATTACHMENTS:

 

1.                     BRT Progress Presentation

 

 

Prepared by:

David Wilkins, Director of Bus Rapid Transit

 

In Collaboration with:

Steven Jones, BRT Outreach Manager

Phillip Halley, Contracts Compliance Administrator

Alieza Bircher, Sr. Project Manager

 

Approved/Reviewed by:

Ramakrishna Pochiraju, Executive Director of Planning & Engineering

Salvador Llamas, Chief Operating Officer

Beverly Greene, Executive Director of External Affairs, Marketing & Communications

Claudia L. Allen, Chief Financial Officer

Jill A. Sprague, General Counsel

William Tonis, Director of Project Controls & Systems Analysis

Derik Calhoun, Director of Transportation

Claudia Burgos, Director of Legislative Affairs & Community Relations