Report ID: 15-210e   
Type: Regular - Planning
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 6/10/2020 Final action: 6/10/2020
Recommended Action: Consider receiving an informational report on the BRT Program budget, O.C. Jones Sons, Inc. contract change orders, and authorizing the General Manager to amend the O.C. Jones and Sons, Inc. contract as-needed up to 30% of the Board-approved contract value for the East Bay Bus Rapid Transit (BRT) Project Infrastructure and Station Platforms.
Sponsors: Board of Directors - Regular Meeting
Attachments: 1. STAFF REPORT, 2. Att.1. BRT Change Order Process Overview, 3. Att.2. Change Order Log, 4. Att.3. Contract Time Extension Summary, 5. Att.4. List of FTA PMOC Reviewed Change Orders, 6. Att.5. Change Order Checklist Template, 7. Master Minute Order
TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager
SUBJECT: BRT Program Budget and Change Orders to Contract 2016-1354

ACTION ITEM

RECOMMENDED ACTION(S):

Title
Consider receiving an informational report on the BRT Program budget, O.C. Jones Sons, Inc. contract change orders, and authorizing the General Manager to amend the O.C. Jones and Sons, Inc. contract as-needed up to 30% of the Board-approved contract value for the East Bay Bus Rapid Transit (BRT) Project Infrastructure and Station Platforms.
Body

STRATEGIC IMPORTANCE:

Goal - Safe and Secure Operations
Initiative - Infrastructure Modernization

Continued budgetary spending authority is critical to the completion of the Bus Rapid Transit project.

BUDGETARY/FISCAL IMPACT:

The original contract value for the BRT Infrastructure and Station Platforms (IFB 2016-1534) was $108,112,200. In September 2019, the Board approved an 18% increase to the original contract value bringing the new contract value to $127,572,396.

BACKGROUND/RATIONALE:

The BRT program (Program) was divided into three construction Packages and an array of supporting professional services. The first two construction packages have been completed; Bid Package 1 - Advanced Utility Relocation, was completed in January 2016; and Bid Package 2 - Parking Lots and Street Improvements, was completed December 2016. Bid Package 3 (BP3) - Infrastructure and Station Platforms (contract 2016-1354), was awarded to O.C. Jones and Sons, Inc (OCJ) on March 9, 2016 (SR 15-210a) and was signed by both parties on March 31, 2016. A Notice to Proceed was issued on August 1, 2016. The baseline program budget for construction and professional services per the Small Starts Grant Agreement (SSGA) was $174,167,885 with November 2017 as revenue service date.

Staff has re-evaluated the Program schedule and costs and with the Board approval revised the Program budget to $232,267,750. The revised Program budget has ...