TO: AC Transit Board of Directors
FROM: Salvador Llamas, General Manager/Chief Executive Officer
SUBJECT: San Pablo Avenue Rapid Corridor Project Evaluation
BRIEFING ITEM
AGENDA PLANNING REQUEST: ☐
RECOMMENDED ACTION(S):
Title
Consider receiving an evaluation report for the San Pablo Avenue Rapid Corridor Project.
Staff Contact:
Ramakrishna Pochiraju, Chief Planning and Development Officer
Body
STRATEGIC IMPORTANCE:
Goal - Convenient and Reliable Service
Initiative - Service Quality
The Rapid Corridors Projects support the District’s Strategic Plan by emphasizing Convenient and Reliable Service. They achieve this through targeted transit priority improvements on busy routes, which enhance transit speed, dependability, and overall service. These improvements include implementing transit signal priority, optimizing signal timings, upgrading bus stops, and increasing accessibility. These investments improve customer experience, ensure more reliable on-time performance, and maintain critical transit infrastructure to deliver consistent, high-quality service to both existing and future riders.
BUDGETARY/FISCAL IMPACT:
There is no fiscal impact associated with receiving the report.
BACKGROUND/RATIONALE:
As part of the San Pablo Rapid Corridor Project, AC Transit upgraded existing transit signal priority (TSP) equipment at 70 intersections along San Pablo Avenue (also known as State Route 123, or SR-123) between Thomas L. Berkley Way (20th St.) in Uptown Oakland to Rumrill Blvd in San Pablo. The updated equipment is more weather-resistant, enables improved signal timing coordination, and uses GPS-based detection, which is more reliable than older infrared-based TSP technology.
Analysis Approach
To evaluate the success of the implemented improvements, AC Transit performed a quantitative assessment of transit performance along the corridor before and after the project. Evaluation objectives, performance measures, and analysis methods are depicted below in Exhibit A, using data from the District’s automatic vehicle location (AVL) system and automatic passenger counters (APCs), big data samples of traffic speeds, and traffic counts.
See Attachment 3 - Exhibit A - Chart of Objectives, Performance Measures, and Analysis Methods
Overview of General Traffic Speeds
General traffic travel speeds during peak congestion times increased modestly between before/after project conditions, while speeds throughout the rest of the day increased more significantly.
The consultant conducted a signalized intersection performance analysis using AVL data to determine how TSP affected bus travel at each intersection and if bus performance traveling through the intersection improved, stayed the same, or deteriorated. The following table summarizes the findings:
See Attachment 3 - Exhibit B - Table of Signalized Intersection Performance Analysis
See Attachment 3 - Exhibit C - Thresholds of Performance Evaluation Criteria
Travel Time Improvement
Average travel speeds for all vehicles during peak congestion times increased modestly between before/after project conditions. However, speeds throughout the rest of the day increased.
See Attachment 3 - Exhibit D - Northbound General Traffic Travel Speeds
See Attachment 3 - Exhibit E - Southbound General Traffic Travel Speeds
End-to-End Transit Travel Times
The project team calculated end-to-end travel times for Line 72 buses between Hilltop Mall and 2nd St. & Washington St. (downtown Oakland) using AVL data and analyzed the data to assess how the Project affected bus travel times and speeds. Bus travel times were consistently shorter in 2024 than in 2019 across all times of day. In most times of day, travel times decreased by approximately five to ten minutes. Exhibits D and E depict the details over the course of the day on weekdays between Fall 2019 and Fall 2024. Average Bus run times during PM peak periods decreased by approximately 5 to 10 minutes.
See Attachment 3 - Exhibit F - Northbound Line 72 End-to-End Travel Times
See Attachment 3 - Exhibit G - Southbound Line 72 End-to-End Travel Times
Improvement in Reliability (On Time Performance, OTP)
Staff evaluated on-time performance (OTP) for lines 72, 72M, and 72R using AVL data to understand if there was an improvement in schedule adherence. Consistent with AC Transit’s policy, a bus was considered “on-time” if it arrived between one minute early and five minutes late of the scheduled time. There was an improvement in on-time performance for most time periods (off peak). Notably, for the former 72R (now the 72L), there was an OTP improvement for all timepoints even in the peak periods. At some timepoints, the improvement was significant enough for the line to meet AC Transit’s agency-wide on-time performance goal where it had not prior to the Project. OTP improved by up to 20% in some cases. During the review period, the District’s OTP KPI was 72%; however, currently the KPI is 75%. In some instances, the improvement was sufficient to meet even the District’s updated OTP KPI. This was not the case for all instances. Lines 72 and 72M suffered a decrease in OTP because of numerous other factors which TSP was unable to overcome.
See Attachment 3 - Exhibit H - Southbound Line 72R On-Time Performance (OTP)
See Attachment 3 - Exhibit I - Northbound Line 72R On-Time Performance (OTP)
Environmental Savings
The California Air Resources Board Emission Factor (EMFAC) 2025 Model was utilized to estimate reductions in fuel use and tailpipe emissions resulting from increased bus operating speeds. For each bus line and direction, non-dwell time was converted into an average moving speed, and related fuel consumption and emission factors per mile at different speeds were obtained from the EMFAC model. During the post-Project analysis, all buses on lines 72, 72M, and 72R operated with diesel engines. This assessment calculated greenhouse gas emission reductions in CO2e (carbon dioxide equivalent), combining CO2, CH4 (methane), and N20 (nitrous oxide) emissions based on Intergovernmental Panel on Climate Change (IPCC) Sixth Assessment Report (AR6) conversion factors. It also evaluated changes in criteria pollutant emissions, including ROG (reactive organic gases), NOx (nitrogen oxides), PM10 (particulate matter of 10μm or less), and CO (carbon monoxide). The table below summarizes the reductions in these four pollutants.
See Attachment 3 - EXHIBIT J - Reduction of Criteria Pollutants (pounds per year)
Benefit-Cost Analysis
The estimated potential savings for the public, bus riders and the District amount to about $27 million over the period of a decade, or approximately $2.7 million in benefits per year, primarily from reduced travel time and fuel use. This is compared to the project's estimated public cost of $3.5 million (inclusive of project management, design, & construction), yielding a benefit-to-cost ratio of nearly 8 to 1.
The benefit-cost analyses utilize the following components of the Project to show the monetary ($) benefits:
Travel time savings, based on the value of time that passengers save. This is calculated with ridership data from February 2024, and the average hourly wage in the Bay Area of $48.19/hour (Bureau of Labor Statistics, May 2025)
Fuel consumption savings, which factors the price of fuel. This analysis uses an assumed fuel cost of $3.87 per gallon, derived from the California Life-Cycle Benefit/Cost Analysis Model (Cal-B/C) Version 8.1
Criteria pollutant and greenhouse gas emissions reduction, which quantifies the health cost of criteria pollutant and greenhouse gas emissions, using factors from the Cal-B/C Version 8.1 model
See Attachment 3 - EXHIBIT K - Monetary Value of Project Benefits
Reducing bus wait times at red lights and travel times cuts fuel use and route duration, helping operators recover faster and improving On Time Performance. These time savings can also lower operational costs if other external factors remain steady. However, operational challenges, route variability, and daily operational adjustments often necessitate schedule modifications, which can delay realizing these savings.
Conclusions & Key Take-aways
Between 2019 and 2024, bus performance on the San Pablo Avenue corridor improved at 68% of signals analyzed, bus travel times decreased, and on-time performance improved. Known changes to the surrounding context make it difficult to determine how much change can be directly attributed to TSP. Staff recommends further evaluation of operational performance at locations that did not improve with TSP to better understand where TSP is less effective and how it can be improved, which may help inform future implementations on other corridors. A controlled study that minimizes external factors other than TSP operations may provide greater clarity into the effects of the Project.
Staff recommends additional improvements along the corridor to enhance the effectiveness of TSP and overall bus performance, including increasing TSP time, relocating more nearside bus stops to far side where feasible, increasing the percentage of trips that start on-time through frequent schedule and layover analysis. Closer coordination between AC Transit and stakeholder/partnering agencies (operating the traffic signals) is needed to ensure that signal timing coordination and parameters (i.e. TSP Green Time) are more supportive of bus throughput.
Next Steps
Staff will bring forward the efficacy of similar TSP projects as evaluation reports become available as well as updates regarding TSP industry advancements. Staff have been monitoring new technological advancements that are integrating Artificial Intelligence (AI) with TSP, promising AI-powered Transit Signal Priority as a cloud-based technology that uses real-time vehicle tracking and AI to dynamically adjust traffic signal timings. If all the traffic signals at every intersection along the San Pablo Corridor were equipped with this advanced technology, there is significant potential to improve how transit buses, vehicles, and people travel along the corridor. This would require commitment and coordination from the regional, county, and local stakeholders.
ADVANTAGES/DISADVANTAGES:
This report does not recommend a course of action with notable advantages or disadvantages. However, there are measurable advantages to implementing TSP upgrades along the San Pablo Corridor. Staff has been able to implement this type of transit priority with less impacts and tradeoffs and with measurable benefit as demonstrated along the corridor.
ALTERNATIVES ANALYSIS:
This report does not recommend an alternative analysis.
PRIOR RELEVANT BOARD ACTION/POLICIES:
18-138a Rapid Corridors Project Design Awards
20-204a Rapid Corridors Project Construction Management Services Award
20-236a Rapid Corridors Project -San Pablo Avenue Construction Award
20-236 Rapid Corridors Project Issuance of an Invitation for Bid
22-315 Rapid Corridors Project Cooperative Agreements
ATTACHMENTS:
1. AC Transit Rapid San Pablo Corridor TSP Project Before and After Evaluation
2. AC Transit Rapid San Pablo Evaluation Summary - Benefit Cost Appendix
3. Tables & Exhibits
Prepared by:
Wil Buller, Traffic Engineer
In Collaboration with:
David Berman, Principal Planner
Approved/Reviewed by:
Ramakrishna Pochiraju, Chief Planning and Development Officer
Robert del Rosario, Director of Services Development & Planning
Aaron Vogel, Chief Operating Officer
Arlee Young, Director of Transportation
Paul Kincaid, Assistant General Manager/Chief Executive Officer
Aimee L. Steele, General Counsel/Chief Legal Officer