Report ID: 19-286   
Type: Regular - Planning
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 9/11/2019 Final action:
Recommended Action: Consider receiving the monthly progress and operational readiness report on the East Bay Bus Rapid Transit (BRT) project.
Sponsors: Board of Directors - Regular Meeting
Attachments: 1. STAFF REPORT, 2. Att. 1 BRT Monthly Progress Report, 3. Master Minute Order

TO:                                          AC Transit Board of Directors                                          

FROM:                                          Michael A. Hursh, General Manager

SUBJECT:                     East Bay Rapid Transit Project Progress Report

                     

BRIEFING ITEM


RECOMMENDED ACTION(S):

 

Title

Consider receiving the monthly progress and operational readiness report on the East Bay Bus Rapid Transit (BRT) project.

 

Body

BUDGETARY/FISCAL IMPACT:

 

Refer to Attachment 1, for the budget status on the construction contract and professional services contracts supporting the BRT Construction and to view the Funding-Expenditure Cost-to-Complete chart.

 

BACKGROUND/RATIONALE:

 

Construction Progress

 

The BRT project has reached 80% project completion with 34 BRT platforms either in interim condition status or under construction. Attachment 1 details month over month construction progress, budget and schedule information.

 

Public Outreach Update

 

The Public Outreach Team continues its daily stakeholder engagement efforts along the BRT corridor, including in-person visits with residents and businesses, email and phone requests for opportunities to present updates, and participation in community festivals and events.  Refer to Attachment 1 for Public Outreach efforts.

Contract Compliance Update

 

The District monitors the contractor and its subcontractors routinely-submitted good faith efforts to hire local residents to the extent practicable.  The region has seen a massive growth in construction projects, limiting the supply of local workers, and as a result, contractors on this project have begun including off-site local hire credit requests, which are now being incorporated into the current percentage. Refer to Attachment 1 for Contract Compliance information.

Operational Readiness Update

 

The Operations teams from Transportation, Planning, Safety, Maintenance and Training continue to meet on a bi-weekly basis to review several elements of the readiness plan. Refer to the Attachment 1 for update from each department and the training program details.

 

 

ADVANTAGES/DISADVANTAGES:

 

This report is a monthly construction update and there are no associated advantages or disadvantages. 

 

ALTERNATIVES ANALYSIS:

 

There is no analysis of alternatives required for this report.

 

PRIOR RELEVANT BOARD ACTION/POLICIES:

 

None


ATTACHMENTS:

1.                     BRT Progress Presentation

 

Approved by:

Ramakrishna Pochiraju, Executive Director of Planning & Engineering

Salvador Llamas, Chief Operating Officer

Beverly Greene, Executive Director of External Affairs, Marketing & Communications

 

Reviewed by:

Denise C. Standridge, General Counsel

Claudia L. Allen, Chief Financial Officer

Claudia Burgos, Director of Legislative Affairs & Community Relations

 

Prepared by:

David Wilkins, Director of Bus Rapid Transit

Steven Jones, BRT Outreach Manager

William Tonis, Director of Project Controls and Systems Analysis

Phillip Halley, Contracts Compliance Administrator

Derik Calhoun, Director of Transportation