TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager/Chief Executive Officer
SUBJECT: MTC OBAG3 Program Funding
ACTION ITEM
AGENDA PLANNING REQUEST: ?
RECOMMENDED ACTION(S):
Title
Consider adoption of Resolution No. 23-003 authorizing the General Manager or his designee to file and execute applications and funding agreements with the Metropolitan Transportation Commission (MTC) for AC Transit's Fruitvale Corridor project.
Staff Contact:
Chris Andrichak, Chief Financial Officer
Body
STRATEGIC IMPORTANCE:
Goal - Financial Stability and Resiliency
Initiative - Financial Efficiency and Revenue Maximization
Securing grant funds for this project will help the District in funding a vital capital project that will improve transit performance.
BUDGETARY/FISCAL IMPACT:
The District was awarded $2 million for the Fruitvale Corridor project for MTC's One Bay Area Grant Cycle 3 (OBAG 3) Program through ACTC's Comprehensive Investment Plan (CIP) in January 2023.
Per MTC guidelines, the District will need to provide a 11.47% local match. With the funding nomination of $2 million, the project's total cost is an estimated $2.23 million. This project will be added to the District's annual capital budget for FY 2024-26. The match will come from a combination of District capital or other grants.
BACKGROUND/RATIONALE:
On June 22, 2022, the Board approved five capital projects for submission to ACTC's CIP program that also met MTC's OBAG 3 funding criteria. On September 1, 2022, ACTC announced that out of the five capital projects that were submitted for consideration, only the Fruitvale Corridor project would be forwarded to MTC for consideration of OBAG 3 funding at a reduced amount of $2 million instead of the requested amount of $3.73 million due to lack of available funding. MTC announced OBAG3 awards on January 11, 2023.
The Fruitvale Corridor project would add Transit Signal Priority (TSP), a queue jump, signal communications an...
Click here for full text