Report ID: 20-345   
Type: Consent
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 9/9/2020 Final action: 9/9/2020
Recommended Action: Consider authorizing the General Manager to execute a contract with Johnson Controls through a Sourcewell cooperative purchasing agreement, formally known as the National Joint Powers Alliance (NJPA), to replace the Division 4 Transportation HVAC chiller.
Attachments: 1. STAFF REPORT, 2. Master Minute Order

TO:                                          AC Transit Board of Directors                                          

FROM:                                          Michael A. Hursh, General Manager

SUBJECT:                     Replacement of the Division 4 Transportation Building HVAC Chiller                       

 

ACTION ITEM


RECOMMENDED ACTION(S):

 

Title

Consider authorizing the General Manager to execute a contract with Johnson Controls through a Sourcewell cooperative purchasing agreement, formally known as the National Joint Powers Alliance (NJPA), to replace the Division 4 Transportation HVAC chiller.

Body

 

STRATEGIC IMPORTANCE:

 

Goal - Safe and Secure Operations

Initiative - Infrastructure Modernization

 

This project will replace an aging chiller unit that frequently breaks down creating a higher maintenance cost with a new dependable and efficient unit that will provide a more stable heating and cooling system for the Division 4 transportation staff.

 

BUDGETARY/FISCAL IMPACT:

 

This project was first included in the FY 19-20 Capital Budget and is continued into the FY 20-21 Capital Budget. Staff is requesting authorization for purchase of the chiller at an estimated cost of $250,000 funded with District Capital.

 

BACKGROUND/RATIONALE:

 

The Heating, Ventilation and Air Conditioning (HVAC) system installed at the D4 transportation building is original to the building utilizing components and technology from 1984. The chiller unit is a component of the HVAC system providing cooling in the summer and is also used to regulate heat during the winter.

 

The current chiller installed at the D4 transportation building is a used unit that was purchased in 2014 as a temporary repair for the original 1984 model. The existing unit has now come to the end of its service life and has become very labor-intensive and costly to maintain.

 

The proposed replacement chiller unit would make the HVAC system more reliable and efficient to operate.

 

ADVANTAGES/DISADVANTAGES:

 

An advantage of approving this project is it will provide a reliable HVAC system, lower maintenance and emergency repair costs.  Provide a suitable temperature controlled working environment during warm weather conditions for a 24-hour office building.

Staff could not identify a disadvantage with approving this project since the system is antiquated and beyond its service life. The current system is more susceptible to issues that would impact the temperature of the D4 transportation building and cause the workspaces of staff to be uncomfortable.

 

ALTERNATIVES ANALYSIS:

 

Staff explored the replacement of the entire HVAC system however the high cost and the potential for not fully utilizing the asset before the building is replaced made this option the least cost-effective.

 

PRIOR RELEVANT BOARD ACTION/POLICIES:

 

Staff Report- 20-062C- New Budget Goals, Proposed FY 2020-21 Budgets, Bi-Monthly Review

 

ATTACHMENTS:

 

None

 

Prepared by:

Chris Durant, Assistant Director of Maintenance

 

In Collaboration with:

Paul Ortiz, Acting Facilities Manager

 

Approved/Reviewed by:

Chris Andrichak, Director of Management and Budget

Cecil Blandon, Director of Maintenance

Joe Callaway, Director of Capital Projects

Salvador Llamas, Chief Operating Officer

Claudia L. Allen, Chief Financial Officer

Jill A. Sprague, General Counsel