AC Transit Logo
 
Report ID: 20-380   
Type: Regular - Planning
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 10/14/2020 Final action: 10/14/2020
Recommended Action: Consider approving the issuance of an Invitation For Bid (IFB) for the construction of Battery Electric Bus Infrastructure at the Emeryville Division (D2).
Attachments: 1. STAFF REPORT, 2. Master Minute Order
TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager
SUBJECT: Battery Electric Bus Infrastructure Construction (Emeryville-D2)

ACTION ITEM

RECOMMENDED ACTION(S):

Title
Consider approving the issuance of an Invitation For Bid (IFB) for the construction of Battery Electric Bus Infrastructure at the Emeryville Division (D2).
Body

STRATEGIC IMPORTANCE:

Goal - Environmental Improvement
Initiative - Infrastructure Modernization

This project will enable the District to provide Battery Electric Bus (BEB) infrastructure to support the Board adopted Zero Emission Bus Rollout Plan.

BUDGETARY/FISCAL IMPACT:

The project is funded by State of California TIRCP Funds and Regional / Local funds from the Bay Area Air Quality Management District (BAAQMD) Carl Moyer Program. This project is funded in the FY 2020-21 Capital Budget. The anticipated construction cost is consistent with the funding allocation in FY2020-21 Capital Improvement Plan. The actual cost estimate is being withheld to ensure that the District receives the best possible pricing during the public bid process.

BACKGROUND/RATIONALE:

In December 2018, the California Air Resources Board (CARB) adopted the Innovative Clean Transit (ICT) regulation that requires California transit agencies to begin purchasing Zero Emission Buses (ZEBs) as early as 2023, with the goal of transitioning all transit buses to zero emission technology by 2040.

On June 10, 2020, the AC Transit Board approved Resolution 20-029 which formally adopted the Zero Emission Bus (ZEB) Rollout Plan as the long-term plan to comply the CARB Innovative Clean Transit Regulation.

This project provides the BEB charging infrastructure necessary to support the next phase of new BEBs deployment planned for the Emeryville (D2) division in FY2022-23. AC Transit plans to install at-grade charging units with manual plug-in cords along the south wall of the existing bus yard. Construction is scheduled for 2021-22 with comp...