Report ID: 20-467c   
Type: Consent
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 3/27/2024 Final action: 3/27/2024
Recommended Action: Consider approving an increase to contract 2022-1540 to GEMS Environmental Services, Inc. for the removal and disposal of unforeseen contaminated soil and water at the Emeryville (D2) Division Underground Tank Removal Project. Staff Contact: Ramakrishna Pochiraju, Executive Director of Planning & Engineering
Attachments: 1. STAFF REPORT, 2. Master Minute Order
TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager/Chief Executive Officer
SUBJECT: GEMS Environmental Services Contract

ACTION ITEM
AGENDA PLANNING REQUEST: ?

RECOMMENDED ACTION(S):

Title
Consider approving an increase to contract 2022-1540 to GEMS Environmental Services, Inc. for the removal and disposal of unforeseen contaminated soil and water at the Emeryville (D2) Division Underground Tank Removal Project.

Staff Contact:
Ramakrishna Pochiraju, Executive Director of Planning & Engineering
Body
STRATEGIC IMPORTANCE:

Goal - Environmental Improvement
Initiative - Infrastructure Modernization

This contract increase will allow the District to remove and dispose of unforeseen contaminated soil and water at D2 in accordance with the directions from and regulations of the Alameda County Department of Environmental Health (ACDEH), and to comply with SB 445 in advance of the statutory deadline.

BUDGETARY/FISCAL IMPACT:

The project is fully funded with State of Good Repair (STA-SGR Capital) funds and has an adequate allocated budget to accommodate this contract increase. The original contract in the amount of $525,803 was approved by Staff Report 20-467a on December 8, 2021.

During the project execution, $59,355 in Contract Change Orders were approved by Staff primarily to provide for compatibility of the day tank on the Division's back-up power generator, bringing the contract total to $585,158.

The proposed $60,000 contract increase raises the total contract value to $645,158 and represents a 22.7% increase above the original contract value as shown below.

The Original Contract Value
$525,803.00
100.00%
Previous Staff Approved Changes
$59,354.96
11.29%
Previous Contract Total
$585,157.96
111.29%
This Change Request
$60,000.00
11.41%
Revised Contract Total
$645,157.96
122.70%


BACKGROUND/RATIONALE:

On December 8, 2021, AC Transit awarded a contract to GEMS Environmental Sys...

Click here for full text