Report ID: 19-030   
Type: Regular - Planning
Meeting Body: Board of Directors - Regular Meeting
Meeting Date: 1/23/2019 Final action: 1/23/2019
Recommended Action: Consider receiving the monthly construction progress report on the East Bay Bus Rapid Transit (BRT) Project for the month of December 2018.
Attachments: 1. STAFF REPORT, 2. Att.1. BRT Monthly Progress Report
TO: AC Transit Board of Directors
FROM: Michael A. Hursh, General Manager
SUBJECT: East Bay Bus Rapid Transit Project Progress Report

BRIEFING ITEM

RECOMMENDED ACTION(S):

Title
Consider receiving the monthly construction progress report on the East Bay Bus Rapid Transit (BRT) Project for the month of December 2018.
Body
BUDGETARY/FISCAL IMPACT:

Refer to Attachment 1, for the budget status on the construction contract and professional services contracts supporting the BRT Construction and to view the Funding-Expenditure Cost-to-Complete chart.
BACKGROUND/RATIONALE:
This report is an update on infrastructure and station platform construction, and community outreach/contract compliance.
Bid Package 3 Infrastructure and Station Platform Project Construction

Construction Progress (CP):
Milestone 1 activities in Segment A (42nd Ave to San Leandro Transit Center) have progressed to interim condition status, except in Zone 9. This means the outside area improvements (curb ramps, sidewalks, drainage, signals, communication conduit and road rehab) and median improvements (median curbs, station platforms and roadway reconstruction) are complete. The electrical contractor Mike Brown Electric (MBE) is energizing and activating portions of the new signal system throughout the segment. A total of 18 BRT platforms (six in San Leandro and twelve in Oakland) comprising 15 BRT stations are in interim condition status and being evaluated for bus docking and alignment issues. Construction activities have started in Zone 9 with survey, staking of work areas and pole foundation placement. Major roadway work is expected to start in January 2019.

Milestone 2 activities in Segment B (20th Street at Broadway to 42nd Avenue) continue in Zones 3 through 6 from 2nd Avenue at Lake Merritt to Derby Avenue in the Fruitvale District. Construction activities include building outside area improvements such as curb ramps, sidewalks, drainage, concrete bus pads, road rehabilitat...